January 2015

Seawall Condition Report

Project is initiated by seawall condition report in 2015.
July 2019

Detailed Planning and Design

05 September → 30 September 2019

Public Exhibition

Council is seeking community feedback on a detailed concept design for the seawall
upgrade. Submissions close at 4.30 PM on Monday 30 September 2019.
October 2019

Review

Thank you for participating by making your submission. The majority of submissions were in favour of the proposed concept design for the Rose Bay Park seawall upgrade. Procurement to award the contract for construction will be finalised by the end of 2019.
December 2019

Construction Works

Works are expected to be completed by June 2020. Residents will be notified before any work starts.